The South African Navy has ordered spare pneumatic cam switching devices from Siemens Ltd for its fleet of three Heroine-class Type 209 diesel-electric attack submarines (SSK). The deal, worth R1 397 438.48,was awarded last week.

The three boats were acquired for R8.1 billion as part of Project Wills,a component of the controversial 1999 Strategic Defence Package. The lead sub, SAS Manthatisi was laid down at Howaldtswerke-Deutsche Werft, Thyssen Nordsee Werke, Kiel on May 22, 2001, was launched June 15, 2004 and commissioned November 3, 2005. She arrived in South African waters in April 2006. Her sisters were both commissioned March 14, 2007. The Charlotte Maxeke arrived in South African waters in April 2007 and SAS Queen Modjadji I in May 2008.

In 2006 then Senior Officer Submarines Captain Malcolm Farre said the government set two main criteria in selecting the T209. The submarine firstly, had to be of a proven design. The T209 has been around since the 1970s and has never suffered a serious design mishap. Secondly, there had to be adequate logistic support, even if support from the primary supplier was interrupted. A dozen navies use about 60 of the type meaning it has a wide global footprint and parts could likely be sourced elsewhere than from source if necessary.

The Type 209 design beat several other offers, including a French offer to upgrade the three Daphné SSKs then in service and a fourth, which was to be donated. A Franco-Spanish consortium also offered two Daphnés as interim vessels while they constructed the Navy a number of CN2000 Scorpéne submarines. Sweden offered the Type 192, an export version of the Gotland-class submarine and Italy proposed Fincantieri’s S1600 design; while Russia suggested its Project 636 Kilo-class boat.

Cabinet in 2006 decided to name the boats for three heroic women in honour of the 50th anniversary of the Woman’s March against the iniquity of pass laws on August 9, 1956. This continued a SA tradition to name submarines after noteworthy women. The previous-generation Daphnés were named for women the National Party regime thought significant: Maria van Riebeeck, Johanna van der Merwe and Emily Hobhouse.

Procurement of spare pneumatic cam switching devices for Type 209, Mod 1400 submarines

EMTM/2010/512 26 May 2011 R1 397 438,48 Siemens Ltd

Procure and commission circuit breaker test facility for Type 209, Mod 1400 submarines

EMTM/2009/559 8 Sep 2010 R15 810 910,00 Siemens Ltd

Maintenance and support services of the command and surveillance general fire control systems and surveillance systems, underwater for the SA Navy

ELGS/2010/11 8 Sep 2010 R48 391 021,90 Cybicom Atlas Defence

Procure and commission circuit breaker test facility for Type 209, Mod 1400 submarines

EMTM/2009/559 8 Sep 2010 R15 810 910,00 Siemens Ltd

Maintenance and support services of the command and surveillance general fire control systems and surveillance systems, underwater for the SA Navy

ELGS/2010/11 8 Sep 2010 R48 391 021,90 Cybicom Atlas Defence

Maintenance and support services for the submarine action information systems for the SA Navy – extension of ELGS/2006/117

LGS/S2009/4274 17 Mar 2010 R2 382 547,02 Cybicom Software

LGS/S2008/3211 19 Feb 2009 R13 691,71 Cybicom Software

LGS/S2008/3871 13 Feb 2009 R4 571 418,63 Cybicom Software

Procurement of type 209 MOD 1400 submarine radar antenna unit

EMTM/2009/304 19 Nov 2009 R2 781 902,78 Marlog Marine Logistik GMBH

Procurement of type 209 model 1400 submarine depot spare parts

EMTM/2008/421 6 Aug 2009 R18 107 215,74 Marlog Marine Logistik GMBH

Alfphastone GmbH

Development and commissioning of a shore based combat suite engineering test bed for the South African Navy Class 209 submarines

EMTM/2008/585 5 Aug 2009 R46 560 029,60 Cybicom Software

Supply and integration of SA Navy class 209 submarine engineering test bed periscope simulator – extension of EMTM/2006/522

MTM/S2007/1373 21 Nov 2007 R113 420,20 Cybicom Software

Engineering test bed periscope simulator for the SA Navy 209 Class Submarine



EMTM/2006/522 5 Jul 2007 R6 985 523,00 Cybicom Software